# Grid feed-in limitation next3 inverter-chargers

**The configuration principle is the same in other countries; you must take your country’s standards into account. This FAQ uses Switzerland as an example.**

Since 1 January 2026, a grid-friendly feed-in regulation has been in force in Switzerland.
 The grid operator decides which installations are affected. The industry recommends that the grid-friendly feed-in regulation should be implemented starting on 1 January 2026 for all solar installations that commission a new inverter.

According to industry guidance (Switzerland), the following are affected:

- New installations for which the connection application (TAG) is received on or after 1 January 2026.
- Existing installations, at the latest when a new inverter is installed.

 

**On the next3, the feed-in limitation must be set for each phase (3):
 /!\ Please refer to the regulations in force in your country for the values you need to apply**

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-1.png)

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-2-300x162.png)

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-3-300x163.png)

 

L1: Parameter ID 2.1.6.10, max. export active power

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-4-300x161.png)

 

L2: Parameter ID 2.1.7.10, max. export active power

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-5-300x162.png)

 

L3: Parameter ID 2.1.8.10, max. export active power

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-6-300x163.png)

 

**Adjust Cos Phi if specified by the electricity supplier in the connection application:**

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-7-300x162.png)

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-8-300x162.png)

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-9-300x163.png)

ID 2.1.5.48 + ID 2.1.5.49 over-excited cos phi capacity + under-excited cos phi capacity

![settings picture next3 feed-in limit](https://studer-innotec.com/wp-content/uploads/2026/10/2610_next3-Feed-in-Limit-10-300x163.png)